| December 5, 2017 |
Campus Work Session #1 |
| December 11 – December 15, 2017 |
Winter Break |
| December 18 – December 22, 2017 |
Project Team Conducting Analyses |
| December 25 – December 29, 2017 |
WOU Campus Closed |
| January 1 – January 5, 2018 |
Project Team Conducting Analyses |
| January 8 – January 12, 2018 |
Athletics & Sustainability Campus Meetings |
| January 15 – January 19, 2018 |
Project Team Conducting Analyses |
| January 22 – January 26, 2018 |
Preparation for Campus Work Session #2 |
| January 29 – February 2, 2018 |
Campus Work Session #2 |
| February 5 – February 9, 2018 |
Phase 1 Report: Existing Conditions |
| February 12 – February 16, 2018 |
Begin Phase 2: Plan Alternatives |